Penfold Review
Contents |
[edit] Introduction
The process of obtaining consent for development is seen by some as a barrier to growth. It can be perceived to be slow and over-bureaucratic, with too many different bodies able to prevent or slow down approval.
Following the recommendations of the Killian Pretty Review in 2008, and in line with the government’s aim ‘…to deregulate and remove barriers to economic growth’, Adrian Penfold was asked to identify whether non-planning consents were delaying or discouraging investment. Non-planning consents are those consents other than planning permission that are required for a development to proceed.
Commissioned the Department of Business Innovation and Skills (BIS), Penfold's remit was ‘…to identify opportunities to deregulate, as a means of supporting business investment in development…’.
The Penfold Review, “Review of non-planning consents” was published on July 18th 2010.
[edit] Findings
The review suggested that non-planning consents did cause delay and uncertainty for development proposals, as well as additional costs. Penfold found that whilst non-planning consents performed a useful role in regulating development (for example; protecting endangered species, tackling climate change, delivering the road network and protecting health and well-being), ‘…the complexity of the non-planning consents landscape and its interaction with the planning system impose additional costs and generate additional risk for businesses. Together, they are a sizeable factor in determining the investment climate in the UK and, therefore, in delivering sustainable development and economic growth’.
In particular, developers highlighted that heritage, highways and environment-related consents were the most problematic.
Penfold found that there was:
- Unnecessary bureaucracy.
- Uncertainty about the time that approvals are likely to take.
- Duplication of roles.
- An absence of a service culture.
- Inconsistency between approving bodies.
- Poor interaction between approving bodies.
- A lack of understanding of the impacts the approval process has on development.
- No standard approval process for developers to follow.
[edit] Recommendations
The review made a great number of recommendations, intended to ‘…increase certainty, speed up processes, reduce duplication and minimise costs’.
These included:
- Strengthening the service culture of consenting bodies.
- Improving co-ordination, collaboration and interaction between consenting bodies and the government departments that oversee them.
- Improving the accessibility of information and guidance.
- Ensuring that once the question of whether a development should happen has been decided, the focus should move to ‘how’ it should happen.
- Simultaneous consideration of issues influencing decisions.
- Wider adoption of best practice.
- Reducing the number of situations in which consents are required.
- Clarifying the boundaries between, and better integrating planning and non-planning consents.
- Combining certain consents, for example; merging conservation area consent with planning permission and combining listed building consent and scheduled monument consent.
The review stopped short of recommending a ‘unified’ consent.
[edit] Impact
In November 2011 the government published the Implementation report on the Penfold Review setting out a programme for the implementation of the review’s recommendations. This included:
- Scrapping unnecessary development consents and simplifying others.
- Reforming the practices of public bodies that grant or advise on development consents.
- Setting a timescale for making decisions on applications.
- Making the application process easier.
In addition, a number of draft improvement plans for key public bodies was published in April 2012 (see the external references at the end of this article), and the Enterprise and Regulatory Reform Bill was drafted, setting out proposals in relation to listed buildings and conservation area consents.
In 2013, the Growth and Infrastructure Act introduced a series of reforms intended to reduce the red tape that the government considers hampers business investment, new infrastructure and job creation. See Growth and Infrastructure Act for more information.
[edit] Related articles on Designing Buildings Wiki
- Conservation area.
- Conservation area consent.
- Enterprise and Regulatory Reform Act 2013.
- Enterprise and Regulatory Reform Act 2013 and listed buildings.
- Growth and Infrastructure Act.
- Killian Pretty Review.
- Listed buildings.
- National Planning Policy Framework.
- Planning permission.
- Planning policy replaced by the NPPF.
- Statutory approvals.
- Statutory authorities.
- Sustainability.
- Taylor Review.
- What approvals are needed before construction begins.
[edit] External references
- Penfold: review of non-planning consents – interim report 2010.
- Penfold: review of non-planning consents – final report 2010.
- Government response to the Penfold Review 2010.
- Implementation report on the Penfold Review 2011.
- Natural England's improvement plan 2012.
- Highway's Agency draft improvement plan 2012.
- RTPI's submission to the Review.
- Written statement by Stephen Hammond, Parliamentary Under Secretary of State for Transport. Proposals to simplify the process of stopping up or diverting a highway will be announced in a consultation response today. 9 January 2013.
- Enterprise and Regulatory Reform Bill.
- The Town and Country Planning (General Development Procedure) Order 1995. Annex A contains full schedule of possible statutory and non-statutory consultees and the circumstance under which they should be consulted.
- Written Ministerial Statement: Implementation of the Penfold Review 16 July 2012.
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.